Zápis z porady / Meetings Minutes
AG TRANSPORT, s.r.o.Průmyslová 1141 686 01 Uherské Hradiště
Místo / Place: onlineDatum / Date: 15.02.2022Čas / Time: 12:00-13:00
Cíl / Meeting Goal: Projects teams cooperation – Borchen, Strassen DE
Účastníci / Participants:
FairWind: Olaf Tomaszewski, Andrzej Szefler, Justyna Dębowska AG TRANSPORT: Tomáš Kepič, Adam Váš,
CC:

Diskuse / Discussion:

IDTéma, Úkol / TaskKdo / ResponsibilityTermín / Due Date
1.Team members introductions for both sides FairWind and AG TRANSPORTOlaf, TomasN/A
2.Projects details and upcoming requirementsOlafN/A
3.Regular projects meetings requirements.Currently – once in 2 weeks, later once every weekDuring project – daily 5-10 min quick update meetingsFairWindAG TRANSPORTN/A
4.Personal jobsite visits – in mid March and then probably in MayFairWindAG TRANSPORTMarch & May
5.Necessarily to provide a complete documentation from AG to FairWind. Risk Assessment, Lifting plans, Transport details and requirementsAG TRANSPORT31.3.2022
6.Risk Assessment – Tomas will send what we currently have, Olaf/Justyna will check if it’s sufficientTomas18.02.2022
7.Possibilities to transport key crawler section on THP modules – Tomas will send an picture to have an ideaTomas18.02.2022
8.Wind reports – mandatory – all cranes must be equipped with online wind data logger accessible via web. For example: www.windcrane.comWhen crane is down and it’s windy a photo proves must be taken in agreed time sequencesOlafAdam31.03.2022
9.If client will require, an anemometr will have to be calibrated. Farwind will confirm with client and inform AG TRANSPORTOlafKW 10
10.German TÜV for both main and auxiliary cranes requirement. Adam will get more info, TÜV will be provided once cranes will be transported to DE, but before project start.Adambefore project start
11.Mobilisation plans – details how AG TRANSPORT plan to mobilize cranes to jobsiteAdam11.03.2022
12.Jobsite crane manager – AG TRANSPORT suggest a main crawler operator to be also a crane manager. FairWind will check if it’s OK.Olaf11.03.2022
13.Drawing check for transport – turning radiuses, el. Wires restrictions etc …Adam, Tomas11.03.2022
14.Possibilities to crawl a crane between towers – if possible. FairWind will check with client and inform a teamOlaf11.03.2022
15.Borchen – tower WEA03 is on 2m foundation as a crawler standing area.
16.Strachen – driving speed restriction – max 10 Km/hour allowed speed. AG will inform all crane crew members about it.Adam, Tomasbefore project
17.FairWind will check possibilities to use a crawler on any other small project between Borchen and Strassen projects pauseOlaf31.03.2022

Příští Porada / Next meeting: end of KW 8/2022